Revenue and Capital Outturn 2019/20

Decision Maker: Cabinet

Decision status: Implemented

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

Report presenting the revenue and capital outturn figures for the financial year 2019/20.

Decisions:

The Cabinet had before it a *report of the Deputy Chief Executive (S151) presenting the revenue and capital outturn figures for the financial year 2019/20.

 

The Cabinet Member for Finance outlined the contents of the report stating that the outturn report was a set of management reports that showed the year end position on all service areas. Appendix 1 showed the overall performance, the recharges and interest charges and that the deficit had been reduced by £20k.  He identified the details of the Housing Revenue Account, the total direct expenditure and income, the development at Palmerston park and the Right to Buys that had been repurchased.  With regard to the Capital Programme, he highlighted the spends to date and the underspend that would be carried forward.  He then thanked the officers within the finance team for their hard work.

 

Consideration was given to:

 

·         A previous request to highlight the 3 Rivers figures on a separate line within the tables

·         The increase in the number of parking permits that had been purchased which had been aided by additional advertising

·         The consultancy budget for the boundary review which had not been required

·         The slippage on the play areas budget which would be rolled forward

 

RESOLVED that:

 

a)    The General Fund outturn achieved in 2019/20 which shows an overall overspend of £232k be noted. This deficit is proposed to be taken from General Fund reserve which will still leave the balance above our minimum recommended level.

 

b)    The net transfers to earmarked reserves of £686k detailed in the General Fund service budget variance reports shown in Appendix 1 and summarised in Appendix 3 be approved.

 

c)    The positive position achieved on the Housing Revenue Account which shows a saving of £608k be noted and the “earmarking” of the extra £608k shown in paragraph 4.2, as well as the utilisation of reserves totalling £859k identified in Appendices 2 be approved; and

 

d)    The carry forward of £9.741m from the 2019/20 capital programme (see paragraph 6.3) be approved as all of the schemes will be delivered in 2020/21 or later years. Also the transfer to earmarked reserves of the un-spent £208k identified in Appendix 4 be approved.

 

(Proposed by Cllr A White and seconded by Cllr L D Taylor)

 

Note:  *Report previously circulated, copy attached to minutes.

Report author: Andrew Jarrett

Publication date: 14/07/2020

Date of decision: 09/07/2020

Decided at meeting: 09/07/2020 - Cabinet

Effective from: 18/07/2020